16150 | Tookany Creek Parkway Bridge Over Tookany Creek (Cheltenham Township, Montgomery County)
This project involves rehabilitating or replacing the weight-limit posted Tookany Creek Parkway bridge over the tributary of the Tookany Creek in Cheltenham Township, just east of New 2nd Street (Bridge Bill 2). A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Over Tookany Creek
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | LOC | $24 | $0 | $0 | $0 | $0 |
FD | STU | $382 | $0 | $0 | $0 | $0 |
FD | 183 | $72 | $0 | $0 | $0 | $0 |
ROW | BOF | $0 | $0 | $0 | $54 | $0 |
ROW | LOC | $0 | $0 | $0 | $3 | $0 |
ROW | 183 | $0 | $0 | $0 | $10 | $0 |
UTL | LOC | $0 | $0 | $0 | $0 | $4 |
UTL | BOF | $0 | $0 | $0 | $0 | $70 |
UTL | 183 | $0 | $0 | $0 | $0 | $13 |
CON | 183 | $0 | $0 | $0 | $0 | $454 |
CON | BOF | $0 | $0 | $0 | $0 | $2419 |
CON | LOC | $0 | $0 | $0 | $0 | $152 |
Program Year Totals: | $478 | $0 | $0 | $67 | ||
Total FY25-FY28 Cost: | $545 | Total FY25-FY36 Cost: | $3,657 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | |
CON | Phase Approved by PMC | |
UTL | Start of Phase | 2008-01-15 |
CON | Cash Flow Start | 2017-06-15 |
CON | Cash Flow End | 2018-05-15 |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Completion of Phase | 2023-05-15 |
UTL | Plan to Utility Unit | 2024-08-15 |
ROW | Plan to ROW Unit | 2024-08-15 |
CON | Let | 2025-04-10 |
CON | Award Contract | 2025-05-10 |
CON | Start of Phase | 2025-06-09 |
CON | Notice to Proceed | 2025-06-09 |
CON | Physical Work Complete | 2026-11-20 |
CON | Project Agreement End Date | 2028-05-20 |