15407 | (SEPTA)
This project will modernize Villanova Station on the Paoli/Thorndale Regional Rail Line, making the station fully ADA accessible, and will advance in phases. Phase 1 ($21M) improved station accessibility and included construction of a new, wider pedestrian tunnel with access ramps and stairs, additional parking spaces, stormwater management improvements, new signage, lighting, and passenger amenities, completed in 2019. Phase 2 ($27M) will make the station fully ADA accessible and includes full length high-level platforms, new canopies, station building improvements, passenger shelters, security improvements and passenger amenities.
The total project cost is $48M. Funding is programmed as follows: Prior year funds in the amount of $22.96M, and $25.06M in FY 2025 - FY 2027.
| Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
|---|---|---|---|---|---|---|
| ERC | 1514 | $4839 | $11613 | $7799 | $0 | $0 |
| ERC | LOC | $161 | $387 | $260 | $0 | $0 |
| Program Year Totals: | $ | $ | $ | $ | ||
| Total FY25-FY28 Cost: | $ | Total FY25-FY36 Cost: | $ | |||
| All costs in thousands. | ||||||