15183 | Station Road Bridge Over Chester Creek (CB #234) (Thornbury Township, Delaware County)
This project involves rehabilitating or replacing Station Road over Chester Creek in Thornbury Township, a single span bridge.
The Station Road bridge is a one lane, reinforced concrete T-beam bridge constructed in 1914 over Chester Creek in Thornbury Township. The width of the bridge is currently 18’-0” due to the numerous bituminous overlays which have concealed the original concrete curbing that previously provided a 16’-8” bridge width. It is currently posted for three tons. The purpose of the project is to correct the structural and safety deficiencies of the bridge to provide a safe and efficient crossing over Chester Creek. The bridge serves residents with local deliveries, school bus transportation, emergency services and access to the local post office located south of the crossing.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | 179 | $12 | $0 | $0 | $0 | $0 |
ROW | BOF | $68 | $0 | $0 | $0 | $0 |
UTL | BOF | $0 | $74 | $0 | $0 | $0 |
UTL | 179 | $0 | $19 | $0 | $0 | $0 |
CON | 179 | $0 | $250 | $258 | $323 | $0 |
CON | BOF | $0 | $1000 | $1032 | $1290 | $0 |
Program Year Totals: | $80 | $1,343 | $1,290 | $1,613 | ||
Total FY25-FY28 Cost: | $4,326 | Total FY25-FY36 Cost: | $4,326 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
ROW | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Completion of Phase | 2017-03-29 |
ROW | Start of Phase | 2020-12-10 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
ROW | Completion of Phase | 2022-12-10 |
CON | Award Contract | 2023-07-22 |
CON | Start of Phase | 2023-08-22 |
CON | Notice to Proceed | 2023-08-22 |
FD | Start of Phase | 2023-10-15 |
FD | PS+E to District Contract Management | 2024-02-15 |
CON | Let | 2024-06-20 |
CON | Physical Work Complete | 2025-08-22 |
CON | Completion of Phase | 2025-10-21 |
CON | Project Agreement End Date | 2027-02-20 |