❮ Back

14581 | US 1 Expressway Reconstruction: PA 896 to PA 41 (Penn Township, East Marlborough Township, Kennett Township, London Grove Township & New Garden Township, Chester County)

The project consists of pavement rehabilitation and reconstruction; guiderail upgrades; vertical and lateral clearance compliance corrections of overhead structures; and interchange improvements such as length of acceleration and deceleration lanes and loop ramp radii. Interchanges included in the work are at PA 796, PA 841 and PA 41. See also MPMS #14580, #113307, and #113312.

Limits: PA 896 to PA 41
Air Quality Code: S10

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FD581$1407$0$0$0$0
FDNHPP$5628$0$0$0$0
ROWSTU$1521$0$0$0$0
UTL581$0$0$0$69$0
UTLSTU$0$0$0$277$0
CONBOF$0$0$0$0$1000
CONSPK-NHPP$0$0$0$15000$15000
CONNHPP$0$0$0$0$50255
CONSTU$0$0$0$0$12213
CON581$0$0$0$3750$19616
Program Year Totals:$8,556$0$0$19,096 
Total FY25-FY28 Cost:$27,652Total FY25-FY36 Cost:$125,736 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
ROWStart of Phase2002-10-15
UTLStart of Phase2003-09-15
UTLCompletion of Phase2010-02-15
ROWCompletion of Phase2010-06-15
FDCompletion of Phase2012-06-15
ROWPhase Approved by PMC
UTLPhase Approved by PMC
FDPhase Approved by PMC
FDPhase on Approved STIP
ROWPhase on Approved STIP
FDStart of Phase2024-03-16
UTLPlan to Utility Unit2024-07-15
ROWPlan to ROW Unit2024-10-15
CONAward Contract2026-01-05
CONStart of Phase2026-02-05
CONNotice to Proceed2026-02-05
FDPS+E to District Contract Management2026-10-15
CONLet2027-01-14
CONCompletion of Phase2029-03-08
CONPhysical Work Complete2029-12-15
CONProject Agreement End Date2031-06-15