❮ Back

14580 | US 1 Expressway Reconstruction: PA 472 to PA 896 (West Nottingham Township, East Nottingham Township, Lower Oxford Township, Oxford Borough & Upper Oxford Township, Chester County)

The project consists of pavement rehabilitation and reconstruction; guiderail upgrades; vertical and lateral clearance compliance corrections of overhead structures; and interchange improvements such as length of acceleration and deceleration lanes and loop ramp radii. Interchanges included in the work are at PA 472, PA 10 and PA 896. See also MPMS #14581, #113307, and #113312.

Limits: PA 472 to PA 896
Air Quality Code: S10

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
ROWSTU$2701$0$0$0$0
UTLSTU*$546$0$0$0$0
CON581$0$608$858$858$20863
CONBOF$0$0$0$0$2000
CONNHPP$0$1632$0$0$0
CONSTU$0$799$3431$3431$81448
Program Year Totals:$3,247$3,039$4,289$4,289 
Total FY25-FY28 Cost:$14,864Total FY25-FY36 Cost:$119,175 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
UTLPhase Approved by PMC
ROWPhase Approved by PMC
ROWStart of Phase2006-11-15
UTLStart of Phase2006-11-15
UTLCompletion of Phase2010-02-15
ROWCompletion of Phase2010-06-15
CONPhase Approved by PMC
UTL4232 Approved by FHWA
ROWPhase on Approved STIP
UTLPhase on Approved STIP
CONPhase on Approved STIP
UTLPlan to Utility Unit2023-01-31
ROWPlan to ROW Unit2023-04-30
CONStart of Phase2025-03-18
CONAward Contract2025-07-16
CONLet2025-07-24
CONNotice to Proceed2025-08-13
CONCompletion of Phase2027-11-02
CONPhysical Work Complete2028-07-15
CONProject Agreement End Date2030-01-13