14580 | US 1 Expressway Reconstruction: PA 472 to PA 896 (West Nottingham Township, East Nottingham Township, Lower Oxford Township, Oxford Borough & Upper Oxford Township, Chester County)
The project consists of pavement rehabilitation and reconstruction; guiderail upgrades; vertical and lateral clearance compliance corrections of overhead structures; and interchange improvements such as length of acceleration and deceleration lanes and loop ramp radii. Interchanges included in the work are at PA 472, PA 10 and PA 896. See also MPMS #14581, #113307, and #113312.
Limits: PA 472 to PA 896
Air Quality Code: S10
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | STU | $2701 | $0 | $0 | $0 | $0 |
UTL | STU* | $546 | $0 | $0 | $0 | $0 |
CON | 581 | $0 | $608 | $858 | $858 | $20863 |
CON | BOF | $0 | $0 | $0 | $0 | $2000 |
CON | NHPP | $0 | $1632 | $0 | $0 | $0 |
CON | STU | $0 | $799 | $3431 | $3431 | $81448 |
Program Year Totals: | $3,247 | $3,039 | $4,289 | $4,289 | ||
Total FY25-FY28 Cost: | $14,864 | Total FY25-FY36 Cost: | $119,175 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
ROW | Start of Phase | 2006-11-15 |
UTL | Start of Phase | 2006-11-15 |
UTL | Completion of Phase | 2010-02-15 |
ROW | Completion of Phase | 2010-06-15 |
CON | Phase Approved by PMC | |
UTL | 4232 Approved by FHWA | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2023-01-31 |
ROW | Plan to ROW Unit | 2023-04-30 |
CON | Start of Phase | 2025-03-18 |
CON | Award Contract | 2025-07-16 |
CON | Let | 2025-07-24 |
CON | Notice to Proceed | 2025-08-13 |
CON | Completion of Phase | 2027-11-02 |
CON | Physical Work Complete | 2028-07-15 |
CON | Project Agreement End Date | 2030-01-13 |