13716 | Headquarters Road Bridge Over Tinicum Creek (Tinicum Township, Bucks County)
This project involves rehabilitating or replacing the Headquarters Road Bridge over Tinicum Creek in Tinicum Township, Bucks County. This bridge is poor condition, functionally obsolete, and currently closed to traffic due to its deteriorated condition. The bridge is a contributing resource to the Ridge Valley Rural Historic District which is listed in the National Register of Historic Places. A final alternative for bridge rehabilitation or replacement is determined upon completion of the review process required by the National Environmental Policy Act (NEPA) and its supporting regulations.
The existing structure is an 80’ long, three-span concrete-encased steel stringer bridge with stone masonry abutments and piers over Tinicum Creek. No utility conflicts are anticipated.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | BOF | $100 | $0 | $0 | $0 | $0 |
Program Year Totals: | $100 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $100 | Total FY25-FY36 Cost: | $100 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Cash Flow Start | 2006-06-15 |
CON | Start of Phase | 2021-10-13 |
CON | Completion of Phase | 2023-05-23 |
CON | Cash Flow End | 2015-10-25 |
CON | Final ROW Clearance | |
CON | Final Utility Clearance | |
CON | 4232 Approved by FHWA | |
CON | Let | 2022-01-13 |
CON | Award Contract | 2022-02-14 |
CON | Notice to Proceed | 2022-04-04 |
CON | Phase on Approved STIP | |
CON | Physical Work Complete | 2023-03-24 |
CON | Reimbursement Agreement | 2023-11-19 |
CON | Project Agreement End Date | 2024-09-21 |