13635 | Oxford Valley Road/Lincoln Highway Intersection Improvements (Falls Township & Middletown Township, Bucks County)
The proposed scope of work includes the reconstruction of N. Oxford Valley Road (SR 2029) as it approaches the Lincoln Highway (SR 2037) intersection from the north and south, in Falls and Middletown Townships, Bucks County, PA. Bristol-Oxford Valley Road (SR 2029) will be re-aligned to intersect N. Oxford Valley Road (SR 2053) to form a new signalized intersection across from the Oxford Point Shopping Center. The project limits extend along SR 2029 1,200 to the south of Lincoln Highway (SR 2037), and 750 to the north of Lincoln Highway (SR 2037). The project limits along SR 2053 begin at the new re-aligned intersection with SR 2029 and extend 383 to the south. The project limits along SR 2037 extend 1,017 to the west of SR 2029, and 930 to the east of SR 2029.
Improvements at the intersection of Oxford Valley Road (SR 2029) and Lincoln Highway (SR 2037) include widening of both roadways for dual left-turn lanes at all 4 (four) approaches to the intersection, and for a northbound right-turn lane. The project includes modification of curb radii and concrete islands, new curb, sidewalk, and ADA compliant curb ramps. The existing traffic signals and mast arms will be replaced, and new drainage structures such as inlets, manholes, and pipes will be installed throughout the project limits. Traffic signal improvements will include signal optimization, emergency pre-emption, and video detection. No structures are included with this project.
Limits: At US 1 and Bristol/Levittown Parkway
Air Quality Code: R1
FY2025 TIP for PA Program Years (in Thousands)
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|
UTL | STU | $796 | $0 | $0 | $0 | $0 |
CON | STU | $3460 | $1460 | $2460 | $2460 | $4000 |
Program Year Totals: | $4,256 | $1,460 | $2,460 | $2,460 | |
Total FY25-FY28 Cost: | $10,636 | Total FY25-FY36 Cost: | $14,636 | |
All costs in thousands. |
Milestones
Phase | Milestone | Estimated Date |
---|
ROW | Phase Approved by PMC | |
ROW | 4232 Approved by FHWA | |
ROW | Start of Phase | |
ROW | Cash Flow Start | 2000-04-14 |
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | 4232 Approved by FHWA | |
ROW | Cash Flow End | 2012-07-22 |
ROW | Completion of Phase | |
UTL | Completion of Phase | |
UTL | Cash Flow Start | 2012-06-22 |
UTL | Start of Phase | 2020-10-15 |
ROW | Plan to ROW Unit | 2021-03-15 |
UTL | Plan to Utility Unit | 2021-03-15 |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Let | 2024-06-20 |
CON | Award Contract | 2024-07-20 |
CON | Start of Phase | 2024-08-19 |
CON | Notice to Proceed | 2024-08-19 |
CON | Completion of Phase | 2026-02-20 |
CON | Physical Work Complete | 2026-08-11 |
CON | Project Agreement End Date | 2028-02-09 |