13240 | Old Bethlehem Road Bridge Over Kimples Creek (Haycock Township, Bucks County)
The project consists of replacing 16' wide weight restricted 13 ton posted bridge over Kimples Creek with a 28' wide bridge with two 11' lanes and 3' shoulders on new alignment. Due to the impacts on emergency services, a temporary roadway and bridge would be required and due to the impacts of the temporary facilities on the wetlands constructing the bridge on a new alignment is the most feasible alternative. As part of the project a wetlands mitigation site will be constructed to mitigate the impacts to the existing wetlands. The existing bridge is posted for 13 tons, shows signs of rapid deterioration, is only 1 lane wide, and has only 111 feet of stopping sight distance. Additionally the horizontal alignment of Old Bethlehem Road north and south of the bridge consists of a series of sharp horizontal curves with substandard sight distance and radii. There is evidence of utility poles being struck.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | 185 | $0 | $368 | $368 | $368 | $0 |
CON | BRIP | $0 | $1477 | $1477 | $1477 | $0 |
Program Year Totals: | $0 | $1,845 | $1,845 | $1,845 | ||
Total FY25-FY28 Cost: | $5,535 | Total FY25-FY36 Cost: | $5,535 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Final Utility Clearance | 2005-01-15 |
CON | Final ROW Clearance | 2005-01-15 |
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Let | 2025-07-10 |
CON | Award Contract | 2025-08-09 |
CON | Start of Phase | 2025-09-08 |
CON | Notice to Proceed | 2025-09-08 |
CON | Physical Work Complete | 2027-07-15 |
CON | Project Agreement End Date | 2029-01-12 |
CON | Completion of Phase | 2029-06-22 |