12965 | Lawn Avenue Reconstruction (Sellersville Borough & West Rockhill Township, Bucks County)
Reconstruct roadway, curbs, sidewalks, and walls. Construct new sidewalk and curbs in areas currently without them. Perform a minor relocation of one horizontal curve. Install new drainage facilities as required. Relocate affected water and sanitary sewer lines as required. A portion of the roadway from Noble St to Maple Ave is proposed to be turned back to the borough upon completion of the project. Upon completion of the project sidewalk will be in place from Grandview Hospital to the borough center.
Limits: Maple Avenue to Farmers Lane
Air Quality Code: S10
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | STU | $0 | $1985 | $1985 | $1985 | $7940 |
CON | 581 | $0 | $496 | $496 | $496 | $1984 |
Program Year Totals: | $0 | $2,481 | $2,481 | $2,481 | ||
Total FY25-FY28 Cost: | $7,443 | Total FY25-FY36 Cost: | $17,367 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | Start of Phase | 2003-11-15 |
CON | Cash Flow Start | 2013-05-15 |
CON | Cash Flow End | 2014-07-15 |
UTL | Completion of Phase | 2017-10-16 |
FD | Completion of Phase | 2020-02-14 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Start of Phase | 2024-02-16 |
UTL | Plan to Utility Unit | 2024-06-19 |
FD | PS+E to District Contract Management | 2025-08-20 |
CON | Let | 2026-04-09 |
CON | Award Contract | 2026-05-09 |
CON | Notice to Proceed | 2026-06-08 |
CON | Start of Phase | 2026-06-08 |
CON | Physical Work Complete | 2027-10-29 |
CON | Completion of Phase | 2027-12-28 |
CON | Project Agreement End Date | 2029-04-28 |