12923 | Bristol Road Extension (Chalfont Borough, New Britain Borough & New Britain Township, Bucks County)
Provide a two lane extension of Bristol Road from Business Route 202 to Park Avenue. When completed, this improvement will provide a two-lane bypass around Chalfont Borough which will eliminate trips on Business Route 202 and turning movements at the Business Route 202/PA 152 intersection. Project may involve relocation of SEPTA siding track, a bridge across the wetlands, widening the intersection at Bristol Road and Business Route 202 to provide right and left turning lanes, providing maintenance of traffic during construction, redesigning traffic signals and rail road crossing gates at Business Route 202 and Bristol Road extension and coordination with SEPTA.
Project CMP (Congestion Management Process) commitments include sidewalks, signal and intersection improvements, turning movement enhancements, and coordination with SEPTA. See DVRPC’s 2016-2017 memorandum on supplemental strategies for details related to this project.
Limits: US 202 to Park Avenue
Air Quality Code: 2035M
FY2025 TIP for PA Program Years (in Thousands)
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|
ROW | TOLL | $0 | $0 | $0 | $0 | $0 |
ROW | STU | $2652 | $0 | $0 | $0 | $0 |
UTL | TOLL | $0 | $0 | $0 | $0 | $0 |
UTL | STU | $0 | $2295 | $0 | $0 | $0 |
CON | 581 | $0 | $1000 | $1000 | $1000 | $4500 |
CON | STU | $0 | $4001 | $4001 | $4001 | $12818 |
CON | STP | $0 | $0 | $0 | $0 | $5184 |
Program Year Totals: | $2,652 | $7,296 | $5,001 | $5,001 | |
Total FY25-FY28 Cost: | $19,950 | Total FY25-FY36 Cost: | $42,452 | |
All costs in thousands. |
Milestones
Phase | Milestone | Estimated Date |
---|
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Completion of Phase | |
UTL | Cash Flow Start | 2010-06-15 |
FD | Phase on Approved STIP | |
FD | Start of Phase | 2023-12-01 |
UTL | Plan to Utility Unit | 2024-01-01 |
ROW | Plan to ROW Unit | 2024-02-01 |
CON | Notice to Proceed | 2025-05-12 |
FD | Completion of Phase | 2025-05-12 |
CON | Start of Phase | 2025-05-12 |
FD | PS+E to District Contract Management | 2025-09-01 |
CON | Let | 2025-12-13 |
CON | Award Contract | 2026-01-12 |
CON | Physical Work Complete | 2027-01-30 |
CON | Completion of Phase | 2027-03-31 |
CON | Project Agreement End Date | 2028-07-30 |