122325 | North Broad Bus-Subway Transfer Improvement Project
This project involves designing and building safer, more attractive bus stops at the intersection of Allegheny Avenue and North Broad Street. Where feasible, elements will include:
-Expanded passenger areas through curb extensions or bus boarding islands;
-Upgraded lighting (e.g. integrated lighting or pedestrian scale lighting);
-Additional trash receptacles;
-Repaired sidewalks;
-Installation of landscaping, planters, and trees;
-Installation of a bus shelter at the northeast corner of Allegheny Avenue and North Broad Street.
The project was allocated funding through the Consolidated Appropriations Act of 2024.
Air Quality Code: S6
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ERC | SXF | $500 | $0 | $0 | $0 | $0 |
ERC | LOC | $125 | $0 | $0 | $0 | $0 |
Program Year Totals: | $625 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $625 | Total FY25-FY36 Cost: | $625 | |||
All costs in thousands. |