119437 | Great Streets Philadelphia RAISE 22 (Philadelphia City)
The City of Philadelphia's capital project will implement critically needed transportation safety improvements, accessibility enhancements, and state of good repair upgrades along seven high crash corridors totaling nearly five miles located in historically disadvantaged communities and areas of persistent poverty. Proposed improvements include traffic safety treatments based on FHWAs Proven Safety Countermeasures, signal modernization, ADA ramps, curb extensions and corner bumpouts, raised crosswalks, RRFB's, resurfacing, and sidewalk upgrades.
Locations include: 57th Street (Upland Way to Wynnefield Avenue); Westminster Avenue (40th to 52nd Streets); Springfield Avenue (51st to 57th Streets); Limekiln Pike (Medary Avenue to Haines Street); Tioga Street (5th to 15th Streets); 11th Street (Master Street to Diamond Street); and Longshore Avenue (Roosevelt Boulevard to Frontenac Street)
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | LOC | $2468 | $0 | $0 | $0 | $0 |
CON | LOC | $0 | $652 | $0 | $0 | $0 |
CON | RAISE | $0 | $25000 | $0 | $0 | $0 |
Program Year Totals: | $2,468 | $25,652 | $0 | $0 | ||
Total FY25-FY28 Cost: | $28,120 | Total FY25-FY36 Cost: | $28,120 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Start of Phase | 2023-01-15 |
PE | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
PE | Completion of Phase | 2023-12-31 |
FD | Start of Phase | 2024-01-15 |
CON | Let | 2026-03-12 |
CON | Award Contract | 2026-04-11 |
FD | Completion of Phase | 2026-05-11 |
CON | Start of Phase | 2026-05-11 |
CON | Notice to Proceed | 2026-05-11 |
CON | Physical Work Complete | 2030-04-01 |
CON | Completion of Phase | 2030-05-31 |
CON | Project Agreement End Date | 2031-09-30 |