❮ Back

119437 | Great Streets Philadelphia RAISE 22 (Philadelphia City)

The City of Philadelphia's capital project will implement critically needed transportation safety improvements, accessibility enhancements, and state of good repair upgrades along seven high crash corridors totaling nearly five miles located in historically disadvantaged communities and areas of persistent poverty. Proposed improvements include traffic safety treatments based on FHWAs Proven Safety Countermeasures, signal modernization, ADA ramps, curb extensions and corner bumpouts, raised crosswalks, RRFB's, resurfacing, and sidewalk upgrades.
Locations include: 57th Street (Upland Way to Wynnefield Avenue); Westminster Avenue (40th to 52nd Streets); Springfield Avenue (51st to 57th Streets); Limekiln Pike (Medary Avenue to Haines Street); Tioga Street (5th to 15th Streets); 11th Street (Master Street to Diamond Street); and Longshore Avenue (Roosevelt Boulevard to Frontenac Street)

Limits: Philadelphia
Air Quality Code: S6

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FDLOC$2468$0$0$0$0
CONLOC$0$652$0$0$0
CONRAISE$0$25000$0$0$0
Program Year Totals:$2,468$25,652$0$0 
Total FY25-FY28 Cost:$28,120Total FY25-FY36 Cost:$28,120 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
PEPhase Approved by PMC
CONPhase Approved by PMC
FDPhase Approved by PMC
PEStart of Phase2023-01-15
PEPhase on Approved STIP
CONPhase on Approved STIP
FDPhase on Approved STIP
PECompletion of Phase2023-12-31
FDStart of Phase2024-01-15
CONLet2026-03-12
CONAward Contract2026-04-11
FDCompletion of Phase2026-05-11
CONStart of Phase2026-05-11
CONNotice to Proceed2026-05-11
CONPhysical Work Complete2030-04-01
CONCompletion of Phase2030-05-31
CONProject Agreement End Date2031-09-30