118425 | Fleecy Dale Road Reconstruction (null County)
This project consists of the reconstruction of Fleecy Dale Rd. Design and construction activities include the addition of a 350' retaining wall along the road adjacent to Paunnacussing Creek and the reconstruction of the roadway.
Limits: Fleecy Dale Road between Old Carversville Road and Fretz Mill Road
Air Quality Code: S10
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | 581 | $95 | $0 | $0 | $0 | $0 |
UTL | 581 | $27 | $0 | $0 | $0 | $0 |
CON | 581 | $2652 | $0 | $0 | $0 | $0 |
Program Year Totals: | $2,774 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $2,774 | Total FY25-FY36 Cost: | $2,774 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
ROW | Plan to ROW Unit | 2022-05-16 |
UTL | Plan to Utility Unit | 2022-05-16 |
PE | Start of Phase | 2022-07-01 |
PE | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
UTL | Start of Phase | 2023-05-01 |
ROW | Start of Phase | 2023-05-01 |
PE | Completion of Phase | 2023-07-31 |
UTL | Completion of Phase | 2024-10-01 |
ROW | Completion of Phase | 2024-10-01 |
CON | Let | 2024-10-10 |
CON | Award Contract | 2024-11-09 |
CON | Start of Phase | 2024-12-09 |
CON | Notice to Proceed | 2024-12-09 |
CON | Physical Work Complete | 2026-01-30 |
CON | Completion of Phase | 2026-03-31 |
CON | Project Agreement End Date | 2027-07-31 |