To design and construct complete street improvements on 5th Street between Roosevelt Boulevard and Godfrey Avenue. Improvements inlcude signal modernization, interconnect, resurfacing, channelization, ADA ramps, safety improvements, and streetlighting
Limits: Roosevelt Blvd. to Godfrey Ave.
0001) to Godfrey Avenue
(SR-4002)
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 581 | $0 | $705 | $0 | $0 | $0 |
CON | STU | $0 | $0 | $0 | $2576 | $0 |
CON | 581 | $0 | $0 | $250 | $644 | $1454 |
CON | STP | $0 | $0 | $1000 | $0 | $5820 |
Program Year Totals: | $0 | $705 | $1,250 | $3,220 | ||
Total FY25-FY28 Cost: | $5,175 | Total FY25-FY36 Cost: | $12,449 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
PE | Start of Phase | 2022-10-30 |
PE | 4232 Approved by FHWA | |
PE | Completion of Phase | 2023-10-30 |
FD | Start of Phase | 2023-10-30 |
FD | Completion of Phase | 2024-10-30 |
CON | Start of Phase | 2025-10-30 |
CON | Completion of Phase | 2028-10-30 |
CON | Project Agreement End Date | 2028-12-29 |