118032 | Dekalb Street Two-Way Reconstruction (Norristown Borough, Montgomery County)
The project will fund full-depth reconstruction of the final remaining segment of US 202 in Montgomery County, along with restriping and traffic signal installation to permit two-way traffic along DeKalb Street in the Municipality of Norristown.
Limits: Lafayette Street to Johnson Highway
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 581 | $318 | $0 | $0 | $0 | $0 |
FD | STP | $1273 | $0 | $0 | $0 | $0 |
ROW | 581 | $0 | $55 | $0 | $0 | $0 |
ROW | STP | $0 | $219 | $0 | $0 | $0 |
UTL | STP | $0 | $0 | $450 | $0 | $0 |
UTL | 581 | $0 | $0 | $113 | $0 | $0 |
CON | 581 | $0 | $0 | $270 | $270 | $810 |
CON | STP | $0 | $0 | $0 | $1080 | $3240 |
CON | STU | $0 | $0 | $1080 | $0 | $0 |
Program Year Totals: | $1,591 | $274 | $1,913 | $1,350 | ||
Total FY25-FY28 Cost: | $5,128 | Total FY25-FY36 Cost: | $9,178 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Start of Phase | 2022-10-30 |
PE | Completion of Phase | 2023-10-30 |
FD | Start of Phase | 2023-10-30 |
ROW | Start of Phase | 2024-10-30 |
UTL | Start of Phase | 2024-10-30 |
FD | Completion of Phase | 2024-10-30 |
UTL | Completion of Phase | 2025-10-30 |
ROW | Completion of Phase | 2025-10-30 |
CON | Start of Phase | 2025-10-30 |
CON | Completion of Phase | 2028-10-30 |