118032 | Dekalb Street Two-Way Reconstruction (Norristown Borough, Montgomery County)

The project will fund full-depth reconstruction of the final remaining segment of US 202 in Montgomery County, along with restriping and traffic signal installation to permit two-way traffic along DeKalb Street in the Municipality of Norristown.

Limits: Lafayette Street to Johnson Highway
Air Quality Code: 2035M

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FD581$318$0$0$0$0
FDSTP$1273$0$0$0$0
ROW581$0$55$0$0$0
ROWSTP$0$219$0$0$0
UTLSTP$0$0$450$0$0
UTL581$0$0$113$0$0
CON581$0$0$270$270$810
CONSTP$0$0$0$1080$3240
CONSTU$0$0$1080$0$0
Program Year Totals:$1,591$274$1,913$1,350 
Total FY25-FY28 Cost:$5,128Total FY25-FY36 Cost:$9,178 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
PEPhase Approved by PMC
PEPhase on Approved STIP
CONPhase Approved by PMC
ROWPhase Approved by PMC
UTLPhase Approved by PMC
FDPhase Approved by PMC
PEStart of Phase2022-10-30
PECompletion of Phase2023-10-30
FDStart of Phase2023-10-30
ROWStart of Phase2024-10-30
UTLStart of Phase2024-10-30
FDCompletion of Phase2024-10-30
UTLCompletion of Phase2025-10-30
ROWCompletion of Phase2025-10-30
CONStart of Phase2025-10-30
CONCompletion of Phase2028-10-30