118031 | PA 29 & PA 113 (Perkiomen Township, Montgomery County)
This project will provide left turn lanes at all four approaches, a right turn lane on the southbound approach of SR 113, update signals and ADA ramps, and provide crosswalks
Limits: Perkiomen Township
Air Quality Code: R1
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | STP | $764 | $0 | $0 | $0 | $0 |
FD | 581 | $191 | $0 | $0 | $0 | $0 |
ROW | 581 | $0 | $328 | $0 | $0 | $0 |
ROW | STP | $0 | $1311 | $0 | $0 | $0 |
UTL | 581 | $0 | $0 | $0 | $0 | $239 |
CON | 581 | $0 | $0 | $0 | $0 | $3582 |
Program Year Totals: | $955 | $1,639 | $0 | $0 | ||
Total FY25-FY28 Cost: | $2,594 | Total FY25-FY36 Cost: | $6,415 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
PE | Start of Phase | 2023-05-01 |
ROW | Start of Phase | 2023-10-30 |
ROW | Completion of Phase | 2024-10-30 |
UTL | Start of Phase | 2024-10-30 |
FD | Completion of Phase | 2024-10-30 |
PE | N. E. P. A. Approval | 2025-01-05 |
PE | Completion of Phase | 2025-02-04 |
FD | Start of Phase | 2025-02-04 |
UTL | Plan to Utility Unit | 2025-09-01 |
ROW | Plan to ROW Unit | 2025-09-01 |
CON | Let | 2025-09-17 |
CON | Award Contract | 2025-10-17 |
CON | Start of Phase | 2025-10-30 |
UTL | Completion of Phase | 2025-10-30 |
FD | PS+E to District Contract Management | 2026-07-01 |
CON | Physical Work Complete | 2026-12-15 |
CON | Completion of Phase | 2027-02-13 |
CON | Project Agreement End Date | 2028-06-14 |