118025 | PA 100 Northbound at Exton Station (West Whiteland Township, Chester County)
The proposed improvements comprise four distinct elements: (1) Addition of a northbound through-lane from Pottstown Pike through the intersection with the US 30 Bypass ramps; (2) Shift the existing travel lanes and the center median to accommodate an additional through-lane, particularly under the Amtrak/SEPTA and Norfolk Southern railroad overpasses; (3) Modifications to Mountain View Drive intersection to retain right-in and right-out access to the Exton Train Station and Courts at Valley View neighborhood; (4) Modifications to Whiteland Woods Boulevard intersection to retain right-in and right-out access.
Limits: PA 100 Northbound
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | STU | $601 | $0 | $0 | $0 | $0 |
UTL | 581 | $0 | $0 | $0 | $0 | $692 |
CON | STP | $0 | $0 | $0 | $0 | $4516 |
CON | 581 | $0 | $0 | $0 | $0 | $1129 |
Program Year Totals: | $601 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $601 | Total FY25-FY36 Cost: | $6,938 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
FD | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
PE | 4232 Approved by FHWA | |
PE | Start of Phase | 2022-12-15 |
PE | Completion of Phase | 2024-10-30 |
UTL | Start of Phase | 2026-10-01 |
FD | Start of Phase | 2026-10-01 |
FD | Completion of Phase | 2028-09-30 |
UTL | Completion of Phase | 2028-10-30 |