118024 | US 202 and High Street Interchange (Westtown Township & West Goshen Township, Chester County)
The scope of the project has three major elements: (1) The addition of one lane inside of the US 202 NB ramp. US 202 NB traffic in the right lane is able to turn onto either ramp lane at the exit. Traffic merging from High Street is stop-controlled; (2) The addition of one lane on the inside of the US 202 SB ramp. The existing center median is converted to an auxiliary merge lane to Old Wilmington Pike so that traffic on SB High Street has more time to merge. The roadway is slightly realigned, but no additional right-of-way is needed; (3) The addition of a left turn lane (40 feet with a 145-foot taper) from EB Matlack Street to NB US 202.
Limits: US 202 Oakburne Road to Matlack Street
Air Quality Code: S2
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 581 | $1591 | $0 | $0 | $0 | $0 |
ROW | STU | $0 | $109 | $0 | $0 | $0 |
UTL | 581 | $0 | $0 | $0 | $174 | $0 |
CON | 581 | $0 | $0 | $0 | $1841 | $7432 |
Program Year Totals: | $1,591 | $109 | $0 | $2,015 | ||
Total FY25-FY28 Cost: | $3,715 | Total FY25-FY36 Cost: | $11,147 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
PE | 4232 Approved by FHWA | |
PE | Start of Phase | 2023-03-30 |
PE | Completion of Phase | 2023-10-30 |
UTL | Start of Phase | 2023-11-01 |
FD | Completion of Phase | 2024-11-01 |
UTL | Completion of Phase | 2024-11-01 |
FD | Start of Phase | 2024-12-30 |
CON | Start of Phase | 2025-10-30 |
CON | Physical Work Complete | 2027-10-30 |
CON | Completion of Phase | 2027-12-29 |
CON | Project Agreement End Date | 2029-04-29 |