118022 | Route 202/179 Roundabout (Solebury Township, Bucks County)

The intersection of Route 202 and Route 179 will be replaced with a roundabout. Surrounding driveways will be realigned to function more efficiently. Pedestrian movements will be improved.

Limits: US 202 and PA 179 Intersection
Air Quality Code: 2035M

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FD581$64$0$0$0$0
FDSTU$255$0$0$0$0
ROWSTU$212$0$0$0$0
ROW581$53$0$0$0$0
UTLSTU$0$219$0$0$0
UTL581$0$55$0$0$0
CONSTU$0$748$1748$1748$2748
CON581$0$187$437$437$687
Program Year Totals:$584$1,209$2,185$2,185 
Total FY25-FY28 Cost:$6,163Total FY25-FY36 Cost:$9,598 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
PEPhase Approved by PMC
PEPhase on Approved STIP
FDPhase Approved by PMC
UTLPhase Approved by PMC
CONPhase Approved by PMC
ROWPhase Approved by PMC
PE4232 Approved by FHWA
PECompletion of Phase2024-10-01
PEStart of Phase2023-03-06
PEN. E. P. A. Approval2024-09-01
FDStart of Phase2024-10-01
ROWStart of Phase2024-10-30
UTLStart of Phase2024-10-30
FDCompletion of Phase2024-10-30
UTLPlan to Utility Unit2024-12-01
ROWPlan to ROW Unit2024-12-01
FDPS+E to District Contract Management2025-09-01
ROWCompletion of Phase2025-10-30
CONStart of Phase2025-10-30
UTLCompletion of Phase2025-10-30
CONLet2025-12-04
CONAward Contract2026-01-03
CONPhysical Work Complete2026-12-31
CONCompletion of Phase2027-03-01
CONProject Agreement End Date2028-06-30