118014 | 2023 Bridge Painting Pkge (Philadelphia City)

This bridge painting project will prevent, delay, or reduce deterioration of bridge elements by painting exposed steel in order to restore the function of several existing bridges, keep them in good or fair condition, thereby extending their service lives without costly rehabilitation projects. Painting steel bridge elements, replacing bridge joints, bearing repairs, and related select steel repairs, all necessitated by failing paint systems.
67730102300033 Northwestern Avenue over Wissahickon Creek;
67730101900042 Southampton Road over Conrail;
67730100200079 Calumet Street over SEPTA;
67730102500094 Red Lion Road over Conrail;
67730100180103 18th Street over Conrail;
67730100900124 49th Street over SEPTA;
67730102700125 42nd Street over AMTRAK and Conrail;
67730100100135 Front Street over Conrail;
67730100100136 Front Street over AMTRAK;
67730100500145 Glenwood Avenue over SEPTA;
67730100600166 Kensington Avenue over Frankford Creek;
67730100300180 McCallum Street over Cresheim Creek;
67730100170234 17th Street over Conrail;
67730100170235 17th Street over SEPTA;
67730100200252 Scotts Lane over Roosevelt Boulevard;
67730100200268 20th Street over Conrail;
67730101300292 Wyoming Avenue over Tacony Creek and Fishers Lane (I Street);
67730100170309 17th Street over Penn Center Underground Street System

Limits: Philadelphia
Air Quality Code: S19

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FD185$0$437$0$0$0
UTLBRIP$0$874$0$0$0
UTLTOLL$0$0$0$0$0
CONTOLL$0$0$0$0$0
CONBRIP$0$0$0$0$6841
CONBOF$0$0$0$0$3900
Program Year Totals:$0$1,311$0$0 
Total FY25-FY28 Cost:$1,311Total FY25-FY36 Cost:$12,052 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONStart of Phase2022-07-01
PEPhase on Approved STIP
FDPhase Approved by PMC
UTLPhase Approved by PMC
CONPhase Approved by PMC
PEPhase Approved by PMC
PEStart of Phase2023-07-31
PECompletion of Phase2025-10-01
CONCompletion of Phase2027-12-30
UTLStart of Phase2028-09-30
FDStart of Phase2028-09-30
FDCompletion of Phase2031-10-01
UTLCompletion of Phase2032-10-01