118006 | Ridley Creek Road over Branch of Ridley Creek (Upper Providence Township, Delaware County)
This project involves rehabilitating or replacing the Bridge at Ridley Creek Road over Branch of Ridley Creek.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
This road segment is included in the Delaware County Bicycle Plan.
Limits: Delaware County
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | TOLL | $0 | $0 | $0 | $0 | $0 |
FD | BRIP | $0 | $563 | $0 | $0 | $0 |
ROW | 183 | $0 | $0 | $0 | $70 | $0 |
ROW | BRIP | $0 | $0 | $0 | $278 | $0 |
UTL | BRIP | $0 | $0 | $0 | $0 | $478 |
UTL | 183 | $0 | $0 | $0 | $0 | $119 |
CON | BRIP | $0 | $0 | $0 | $0 | $984 |
CON | 183 | $0 | $0 | $0 | $0 | $246 |
Program Year Totals: | $0 | $563 | $0 | $348 | ||
Total FY25-FY28 Cost: | $911 | Total FY25-FY36 Cost: | $2,738 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Award Contract | 2022-07-01 |
CON | Start of Phase | 2022-07-31 |
CON | Notice to Proceed | 2022-07-31 |
FD | Completion of Phase | 2022-07-31 |
CON | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Start of Phase | 2023-10-01 |
CON | Completion of Phase | 2027-12-30 |