117999 | Thomas Road over Trout Creek (CB #300) (Tredyffrin Township, Chester County)
This project involves rehabilitating or replacing the Bridge at Thomas Road over Trout Creek in Tredyffrin Township (CB #300).
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: Thomas Road
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 183 | $546 | $0 | $0 | $0 | $0 |
ROW | 183 | $0 | $56 | $0 | $0 | $0 |
UTL | 183 | $0 | $0 | $0 | $0 | $69 |
CON | 183 | $0 | $0 | $0 | $0 | $955 |
CON | BRIP | $0 | $0 | $0 | $0 | $3820 |
Program Year Totals: | $546 | $56 | $0 | $0 | ||
Total FY25-FY28 Cost: | $602 | Total FY25-FY36 Cost: | $5,446 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Start of Phase | 2022-07-01 |
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Start of Phase | 2023-04-05 |
ROW | Start of Phase | 2023-10-01 |
UTL | Start of Phase | 2023-10-01 |
PE | Completion of Phase | 2023-10-01 |
UTL | Completion of Phase | 2024-10-30 |
ROW | Completion of Phase | 2024-10-30 |
FD | Completion of Phase | 2024-10-30 |
FD | Start of Phase | 2025-01-15 |
CON | Completion of Phase | 2028-12-30 |