116893 | Edison Furlong Road Bridge over Pebble Creek (Buckingham Township, Bucks County)
Improvements include replacing the scour damaged bridge over Pebble Creek pursuant to damage caused by Hurricane Ida.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Edison Furlong o/ Pebble Creek
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | STP | $800 | $0 | $0 | $0 | $0 |
Program Year Totals: | $800 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $800 | Total FY25-FY36 Cost: | $800 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase on Approved STIP | |
PE | Phase on Approved STIP | |
PE | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
PE | Start of Phase | 2022-12-05 |
PE | 4232 Approved by FHWA | |
PE | N. E. P. A. Approval | 2024-05-31 |
FD | Start of Phase | 2024-06-30 |
PE | Completion of Phase | 2024-06-30 |
FD | PS+E to District Contract Management | 2025-09-11 |
CON | Let | 2025-12-11 |
CON | Award Contract | 2026-01-10 |
CON | Start of Phase | 2026-02-09 |
CON | Notice to Proceed | 2026-02-09 |
FD | Completion of Phase | 2026-02-09 |
CON | Physical Work Complete | 2026-10-30 |
CON | Completion of Phase | 2026-12-29 |
CON | Project Agreement End Date | 2028-04-29 |