❮ Back

116807 | Citywide ADA Ramps 4 (Philadelphia City)

This "Transition List" project will include the design and construction of ADA ramps that were originally included in the scope of other federal aid projects as well as various streetscape projects and ramps located on select Federal Aid routes that were repaved with local funding. These ramps typically would be included as design build items in the original project contracts, however, in some instances, the urban context of the ADA ramp locations warrants further coordination or study. To allow the original construction projects to proceed in a timely fashion, these ramps were pulled from the original construction contracts and will now be addressed as part of this transition list package. This will allow the City to design and construct the ramps to meet current ADA requirements while properly providing for stairs, cellar doors, unique paving materials, adjacent historic properties and other considerations as necessary.

Limits: City of Philadelphia
Air Quality Code: A2

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FDSTP$720$0$0$0$0
FDLOC$180$0$0$0$0
CONSTP$0$1855$1000$2005$4415
CONLOC$0$464$250$501$1104
Program Year Totals:$900$2,319$1,250$2,506 
Total FY25-FY28 Cost:$6,975Total FY25-FY36 Cost:$12,494 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
PEPhase Approved by PMC
PEPhase on Approved STIP
FDPhase on Approved STIP
CONPhase Approved by PMC
FDPhase Approved by PMC
PEStart of Phase2022-12-21
FDStart of Phase2023-12-15
PECompletion of Phase2023-12-21
FDPS+E to District Contract Management2024-12-15
CONLet2025-03-13
CONAward Contract2025-04-12
CONStart of Phase2025-05-12
FDCompletion of Phase2025-05-12
CONNotice to Proceed2025-05-12
CONPhysical Work Complete2027-03-15
CONCompletion of Phase2027-05-14
CONProject Agreement End Date2028-09-12