116807 | Citywide ADA Ramps 4 (Philadelphia City)
This "Transition List" project will include the design and construction of ADA ramps that were originally included in the scope of other federal aid projects as well as various streetscape projects and ramps located on select Federal Aid routes that were repaved with local funding. These ramps typically would be included as design build items in the original project contracts, however, in some instances, the urban context of the ADA ramp locations warrants further coordination or study. To allow the original construction projects to proceed in a timely fashion, these ramps were pulled from the original construction contracts and will now be addressed as part of this transition list package. This will allow the City to design and construct the ramps to meet current ADA requirements while properly providing for stairs, cellar doors, unique paving materials, adjacent historic properties and other considerations as necessary.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | STP | $720 | $0 | $0 | $0 | $0 |
FD | LOC | $180 | $0 | $0 | $0 | $0 |
CON | STP | $0 | $1855 | $1000 | $2005 | $4415 |
CON | LOC | $0 | $464 | $250 | $501 | $1104 |
Program Year Totals: | $900 | $2,319 | $1,250 | $2,506 | ||
Total FY25-FY28 Cost: | $6,975 | Total FY25-FY36 Cost: | $12,494 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Start of Phase | 2022-12-21 |
FD | Start of Phase | 2023-12-15 |
PE | Completion of Phase | 2023-12-21 |
FD | PS+E to District Contract Management | 2024-12-15 |
CON | Let | 2025-03-13 |
CON | Award Contract | 2025-04-12 |
CON | Start of Phase | 2025-05-12 |
FD | Completion of Phase | 2025-05-12 |
CON | Notice to Proceed | 2025-05-12 |
CON | Physical Work Complete | 2027-03-15 |
CON | Completion of Phase | 2027-05-14 |
CON | Project Agreement End Date | 2028-09-12 |