115445 | 5th Street Corridor Safety Improvements (Philadelphia City)
This project will implement countermeasures to improve safety along local route 5th St from Spring Garden St to Erie Ave in the City of Philadelphia. Pedestal mounted signal heads will be converted to overhead mast arms to improve visibility of signal heads at intersections. Pedestrian safety improvements include the addition of pedestrian countdown signals as part of the intersection improvements.
Limits: Spring Garden Street to Erie Avenue
Air Quality Code: S6
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | HSIP | $0 | $7500 | $0 | $0 | $0 |
Program Year Totals: | $0 | $7,500 | $0 | $0 | ||
Total FY25-FY28 Cost: | $7,500 | Total FY25-FY36 Cost: | $7,500 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Start of Phase | 2023-05-01 |
FD | PS+E to District Contract Management | 2025-11-01 |
CON | Let | 2026-02-12 |
CON | Award Contract | 2026-03-14 |
FD | Completion of Phase | 2026-04-13 |
CON | Start of Phase | 2026-04-13 |
CON | Notice to Proceed | 2026-04-13 |
CON | Physical Work Complete | 2027-07-01 |
CON | Completion of Phase | 2027-08-30 |
CON | Project Agreement End Date | 2028-12-29 |