The proposed scope of this project include:
• Adding lane lines on corridor – the corridor is two lanes in each direction for the majority of the length but pavement markings are not currently visible to drivers.
• Upgrading signal equipment by replacing 8” signal heads with 12” signal heads, installing retroflective back plates, adding additional signal heads (one for each lane, currently only one head per approach), installing countdown pedestrian signal heads.
• Evaluating and updating left-turn phasing at several intersections with a high number of angle crashes for left-turning vehicles.
• Evaluating and updating vehicle and pedestrian clearance timings.
• Convert the signalized intersection of Cobbs Creek Parkway (SR 3015) and Spruce Street/Marshall Road (SR 3031) to a single-lane roundabout.

Limits: 63rd Street/Cobbs Creek Parkway corridor from Lancaster Ave (SR 0030) to 62nd Street

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
CONSTU$0$0$0$0$3571
FDHSIP$1500$1500$0$0$0
CON581$0$0$0$0$20551
FDTOLL$0$0$0$0$0
UTLTOLL$0$0$0$0$0
UTLHSIP$0$500$0$0$0
Program Year Totals:$$$$ 
Total FY25-FY28 Cost:$Total FY25-FY36 Cost:$ 
All costs in thousands.

No milestones are available for this project.