115435 | 63rd Street Corridor Safety Improvements (Philadelphia City)
The proposed scope of this project include:
• Adding lane lines on corridor – the corridor is two lanes in each direction for the majority of the length but pavement markings are not currently visible to drivers.
• Upgrading signal equipment by replacing 8” signal heads with 12” signal heads, installing retroflective back plates, adding additional signal heads (one for each lane, currently only one head per approach), installing countdown pedestrian signal heads.
• Evaluating and updating left-turn phasing at several intersections with a high number of angle crashes for left-turning vehicles.
• Evaluating and updating vehicle and pedestrian clearance timings.
• Convert the signalized intersection of Cobbs Creek Parkway (SR 3015) and Spruce Street/Marshall Road (SR 3031) to a single-lane roundabout.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | HSIP | $1500 | $1500 | $0 | $0 | $0 |
FD | TOLL | $0 | $0 | $0 | $0 | $0 |
UTL | HSIP | $0 | $500 | $0 | $0 | $0 |
UTL | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | 581 | $0 | $0 | $0 | $0 | $29851 |
CON | STU | $0 | $0 | $0 | $0 | $3571 |
Program Year Totals: | $1,500 | $2,000 | $0 | $0 | ||
Total FY25-FY28 Cost: | $3,500 | Total FY25-FY36 Cost: | $36,922 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
FD | Start of Phase | 2022-02-01 |
ROW | Start of Phase | 2022-02-01 |
ROW | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Completion of Phase | 2022-10-01 |
CON | Let | 2024-01-25 |
CON | Award Contract | 2024-02-24 |
CON | Start of Phase | 2024-03-25 |
FD | Completion of Phase | 2024-03-25 |
CON | Notice to Proceed | 2024-03-25 |
CON | Physical Work Complete | 2024-03-31 |
CON | Completion of Phase | 2024-05-30 |
CON | Project Agreement End Date | 2025-09-29 |