115434 | Frankford Avenue Corridor Safety Improvements (Philadelphia City)
The proposed scope of this project include:
Convert signals from pedestal-mounted to mast arm
Add pedestrian countdown timers
Install retroreflective backplates
Upgrade signal cabinets
Coordinate arterial signals at the following intersections:
Berks St
Norris St
Susquehanna Ave
Dauphin St
Cumberland St
Huntingdon St
Somerset St
Cambria St
Orleans St
Ann St
Westmoreland St
Venango St
Glenwood Ave
Pike St
Torresdale Ave
Convert minor road stop control to all-way stop control at Palmer St
Install curb extensions
Install ADA ramps
Install intersection lighting over crossings
Limits: Oxford St to Convent Lane
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | TOLL | $0 | $0 | $0 | $0 | $0 |
FD | HSIP | $313 | $0 | $0 | $0 | $0 |
CON | HSIP | $2376 | $2375 | $0 | $0 | $0 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
Program Year Totals: | $2,689 | $2,375 | $0 | $0 | ||
Total FY25-FY28 Cost: | $5,064 | Total FY25-FY36 Cost: | $5,064 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Start of Phase | 2023-12-01 |
FD | PS+E to District Contract Management | 2024-09-01 |
CON | Let | 2025-03-13 |
CON | Award Contract | 2025-04-12 |
FD | Completion of Phase | 2025-05-12 |
CON | Start of Phase | 2025-05-12 |
CON | Notice to Proceed | 2025-05-12 |
CON | Physical Work Complete | 2026-11-30 |
CON | Completion of Phase | 2027-01-29 |
CON | Project Agreement End Date | 2028-05-30 |