115429 | Belmont Avenue and St. Asaphs Road Roundabout (Lower Merion Township, Montgomery County)
This project will implement a roundabout at the intersection of Belmont Avenue and St. Asaphs Road in Lower Merion Township, Montgomery County.
Limits: Belmont Avenue (SR 3045) and St Asaphs Road intersection
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | HSIP | $220 | $0 | $0 | $0 | $0 |
ROW | HSIP | $427 | $0 | $0 | $0 | $0 |
UTL | HSIP | $0 | $41 | $0 | $0 | $0 |
CON | HSIP | $0 | $0 | $2119 | $0 | $0 |
Program Year Totals: | $647 | $41 | $2,119 | $0 | ||
Total FY25-FY28 Cost: | $2,807 | Total FY25-FY36 Cost: | $2,807 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2022-01-02 |
UTL | Start of Phase | 2022-01-02 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Completion of Phase | 2023-07-01 |
ROW | Completion of Phase | 2023-07-01 |
FD | Start of Phase | 2023-07-31 |
FD | Completion of Phase | 2024-09-23 |
UTL | Plan to Utility Unit | 2024-11-01 |
ROW | Plan to ROW Unit | 2024-12-01 |
FD | PS+E to District Contract Management | 2026-09-01 |
CON | Let | 2027-01-15 |
CON | Award Contract | 2027-02-14 |
CON | Start of Phase | 2027-03-16 |
CON | Notice to Proceed | 2027-03-16 |
CON | Physical Work Complete | 2028-07-30 |
CON | Completion of Phase | 2028-09-28 |
CON | Project Agreement End Date | 2030-01-28 |