❮ Back

115428 | Sumneytown Pike Intersections Safety Improvements (Salford Township, Montgomery County)

Construction of left-turn lanes on PA 63 at 2 intersections.
Install exclusive left turn lanes to make traffic flow improvements at Barndt Road (2 left turn lanes), Ridge Road/Skippack Road (2 left turn lanes), geometric improvement to remove skew angle of Ridge Road at Sumneytown Pike.

Limits: Intersections of Sumneytown Pk and Barndt Rd, Ridge Rd/Skippack Rd
Air Quality Code: R1

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FDHSIP$650$0$0$0$0
ROWHSIP$0$500$0$0$0
UTLHSIP$0$719$0$0$0
CONHSIP$0$0$4750$0$0
Program Year Totals:$650$1,219$4,750$0 
Total FY25-FY28 Cost:$6,619Total FY25-FY36 Cost:$6,619 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
CONPhase Approved by PMC
ROWPhase Approved by PMC
UTLPhase Approved by PMC
UTLStart of Phase2021-10-01
FDPhase on Approved STIP
CONPhase on Approved STIP
ROWPhase on Approved STIP
UTLPhase on Approved STIP
ROWStart of Phase2022-10-01
UTLCompletion of Phase2022-10-31
ROWCompletion of Phase2023-10-31
FDStart of Phase2023-12-01
UTLPlan to Utility Unit2024-04-01
ROWPlan to ROW Unit2024-05-01
FDCompletion of Phase2025-08-25
FDPS+E to District Contract Management2026-09-01
CONLet2027-01-15
CONAward Contract2027-02-14
CONStart of Phase2027-03-16
CONNotice to Proceed2027-03-16
CONPhysical Work Complete2028-09-01
CONCompletion of Phase2028-10-31
CONProject Agreement End Date2030-03-02