115427 | Lansdowne Avenue Corridor Safety Improvements (Yeadon Borough, Darby Borough & Lansdowne Borough, Delaware County)
The proposed scope of this project include:
• Installation of retroreflective backplates on signals
• Addition of pedestrian countdown timers at signalized intersections
• Installation of additional lighting at the following intersections:
o Mercy Fitzgerald Hospital
o Baily Road
o Providence Road
o Stewart Avenue
o Greenwood Avenue
o Essex Avenue
o Plumstead Avenue
o Marshall Road
• Coordination of arterial signals at the following intersections:
o Mercy Fitzgerald Hospital
o Baily Road
o Providence Road
o Baltimore Avenue
o Stewart Avenue
o Greenwood Avenue
o Essex Avenue
o Plumstead Avenue
o Marshall Road
• Installation of mast arms for each approach at the following intersections:
o Stewart Avenue
o Greenwood Avenue
o Marshall Road
• Installation of raised crosswalks at Stewart Avenue
• Installation of high visibility crosswalk and rapid flashing beacon at Lansdowne Theater
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | CRPU | $1300 | $0 | $0 | $0 | $0 |
CON | sHSIP | $3600 | $0 | $0 | $0 | $0 |
CON | HSIP | $2026 | $0 | $0 | $0 | $0 |
Program Year Totals: | $6,926 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $6,926 | Total FY25-FY36 Cost: | $6,926 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Start of Phase | 2023-10-01 |
FD | PS+E to District Contract Management | 2024-12-01 |
CON | Let | 2025-03-13 |
CON | Award Contract | 2025-04-12 |
FD | Completion of Phase | 2025-05-12 |
CON | Start of Phase | 2025-05-12 |
CON | Notice to Proceed | 2025-05-12 |
CON | Physical Work Complete | 2026-07-01 |
CON | Completion of Phase | 2026-08-30 |
CON | Project Agreement End Date | 2027-12-30 |