115426 | Haverford Road Corridor Safety Improvements (Haverford Township, Delaware County)
The proposed scope of this project include:
• Road Diet of Haverford Road from Landover Road (SR 1001) to Karakung Road/Winchester Road
• Addition of two-way left-turn lane from Landover Road (SR 1001) to Karakung Road/Winchester Road
• Addition of exclusive left-turn lane(s) on Haverford Road (SR 1001) at the following intersections:
o Landover Road (2 LTLs)
o Buck Lane (2 LTLs)
o Hathaway Lane (1 LTL)
o Loraine Street (1 LTL)
o Eagle Road (2 LTLs)
• Modification of left turn signal phasing at the following intersections:
o Landover Road (2 approaches)
o Buck Lane (2 approaches)
o College Avenue (2 approaches)
o Ardmore Avenue (1 approach)
o Eagle Road (2 approaches)
o Karakung Road (1 approach)
• Installation of dynamic signal warning flashers at the following intersections:
o Buck Lane (1 approach)
o College Avenue (1 approach)
o Ardmore Avenue (1 approach)
o Eagle Road (1 approach)
• Installation of actuated advance warning dilemma zone protection system for Haverford Road (SR 1001) at the following intersections:
o Landover Road
o Buck Lane
o College Avenue
o Ardmore Avenue
o Hathaway Lane
o Loraine Street
o Eagle Road
o Karakung Road
This road segment is included in the Delaware County Bicycle Plan.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | HSIP | $1866 | $0 | $0 | $0 | $0 |
Program Year Totals: | $1,866 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $1,866 | Total FY25-FY36 Cost: | $1,866 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Completion of Phase | 2023-01-02 |
FD | Start of Phase | 2023-04-14 |
FD | PS+E to District Contract Management | 2024-09-01 |
CON | Let | 2025-01-16 |
CON | Award Contract | 2025-02-15 |
CON | Start of Phase | 2025-03-17 |
CON | Notice to Proceed | 2025-03-17 |
CON | Physical Work Complete | 2025-12-30 |
CON | Completion of Phase | 2026-02-28 |
CON | Project Agreement End Date | 2027-06-30 |