115423 | Route 23 Corridor Safety Improvements (Phoenixville Borough, East Pikeland Township & Schuylkill Township, Chester County)
The proposed scope of this project include:
• Installation of retroreflective backplates on signals
• Addition of pedestrian countdown timers and pushbuttons at signalized intersections
• Modification of signal phasing to include a leading pedestrian interval at Rapps Dam Road/Mowere Road intersection
• Installation of a signal at Mason Street intersection
• Installation of intersection warning signage at Second Avenue/Buchanan Street intersection
• Installation of signal ahead signage at the following intersections:
o Bridge Street/Mellon Street
o Main Street/Manavon Street
• Eliminate passing lane on eastbound SR 0023 at Kimberton Road intersection
Limits: From Ridge Road to Whitehorse Road
Air Quality Code: S6
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | HSIP | $3000 | $0 | $0 | $0 | $0 |
Program Year Totals: | $3,000 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $3,000 | Total FY25-FY36 Cost: | $3,000 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Start of Phase | 2022-10-27 |
FD | 4232 Approved by FHWA | |
FD | Completion of Phase | 2024-06-24 |
FD | PS+E to District Contract Management | 2024-12-02 |
CON | Let | 2025-04-10 |
CON | Award Contract | 2025-05-10 |
CON | Start of Phase | 2025-06-09 |
CON | Notice to Proceed | 2025-06-09 |
CON | Physical Work Complete | 2026-08-01 |
CON | Completion of Phase | 2026-09-30 |
CON | Project Agreement End Date | 2028-01-30 |