115419 | US 202/Route 263 (York Road) Roundabout (Buckingham Township, Bucks County)
This project is for the implementation of a roundabout at US 202/Route 263 & York Road.
Limits: US 202 & York Road
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | HSIP | $1115 | $0 | $0 | $0 | $0 |
UTL | HSIP | $33 | $0 | $0 | $0 | $0 |
CON | HSIP | $0 | $1582 | $0 | $0 | $0 |
Program Year Totals: | $1,148 | $1,582 | $0 | $0 | ||
Total FY25-FY28 Cost: | $2,730 | Total FY25-FY36 Cost: | $2,730 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2022-06-01 |
UTL | Start of Phase | 2022-06-01 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Completion of Phase | 2022-11-01 |
ROW | Completion of Phase | 2022-11-01 |
FD | Start of Phase | 2023-07-01 |
UTL | Plan to Utility Unit | 2023-08-01 |
ROW | Plan to ROW Unit | 2023-09-01 |
FD | Completion of Phase | 2024-12-23 |
FD | PS+E to District Contract Management | 2025-12-01 |
CON | Let | 2027-01-15 |
CON | Award Contract | 2027-02-14 |
CON | Start of Phase | 2027-03-16 |
CON | Notice to Proceed | 2027-03-16 |
CON | Physical Work Complete | 2028-10-01 |
CON | Completion of Phase | 2028-11-30 |
CON | Project Agreement End Date | 2030-04-01 |