115418 | Route 113 & Minsi Trail Road Roundabout (Hilltown Township, Bucks County)
This project is for the implementation of a roundabout at Souderton Road (SR 113) and Minsi Trail Road (SR 4019).
Limits: Souderton Road and Minsi Trail
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | HSIP | $263 | $0 | $0 | $0 | $0 |
UTL | HSIP | $23 | $0 | $0 | $0 | $0 |
CON | HSIP | $0 | $1061 | $0 | $0 | $0 |
Program Year Totals: | $286 | $1,061 | $0 | $0 | ||
Total FY25-FY28 Cost: | $1,347 | Total FY25-FY36 Cost: | $1,347 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2022-04-01 |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
UTL | Completion of Phase | 2022-12-01 |
UTL | Start of Phase | 2023-04-01 |
UTL | Plan to Utility Unit | 2023-07-01 |
FD | Start of Phase | 2023-07-01 |
ROW | Completion of Phase | 2023-10-01 |
ROW | Plan to ROW Unit | 2023-11-01 |
FD | PS+E to District Contract Management | 2026-09-01 |
CON | Let | 2027-01-15 |
CON | Award Contract | 2027-02-14 |
CON | Start of Phase | 2027-03-16 |
CON | Notice to Proceed | 2027-03-16 |
FD | Completion of Phase | 2027-03-16 |
CON | Physical Work Complete | 2027-10-31 |
CON | Completion of Phase | 2027-12-30 |
CON | Project Agreement End Date | 2029-04-30 |