114948 | Lancaster Avenue and Remington Road Intersection Improvements (Lower Merion Township, Montgomery County)
The scope of this project entails safety countermeasures which include:
1) Expanding from a four lane to five lane section along Lancaster Ave to add left turn lanes.
2) Install pedestrian countdown timers
3) Add signal (additional primary head) on the mast arms along Remington Road.
4) Provide ADA ramps
5) Upgrade existing mast arms
Limits: Lancaster Ave and Remington Rd
Air Quality Code: R1
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | sHSIP | $90 | $0 | $0 | $0 | $0 |
ROW | sHSIP | $100 | $0 | $0 | $0 | $0 |
UTL | sHSIP | $50 | $0 | $0 | $0 | $0 |
CON | sHSIP | $0 | $0 | $1202 | $0 | $0 |
Program Year Totals: | $240 | $0 | $1,202 | $0 | ||
Total FY25-FY28 Cost: | $1,442 | Total FY25-FY36 Cost: | $1,442 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
ROW | Start of Phase | 2021-01-01 |
UTL | Completion of Phase | 2021-01-31 |
ROW | Completion of Phase | 2021-04-01 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2023-05-01 |
FD | Start of Phase | 2023-08-31 |
UTL | Start of Phase | 2024-02-01 |
ROW | Plan to ROW Unit | 2024-04-01 |
FD | Completion of Phase | 2025-08-25 |
FD | PS+E to District Contract Management | 2026-09-01 |
CON | Let | 2027-01-15 |
CON | Award Contract | 2027-02-14 |
CON | Start of Phase | 2027-03-16 |
CON | Notice to Proceed | 2027-03-16 |
CON | Physical Work Complete | 2027-10-30 |
CON | Completion of Phase | 2027-12-29 |
CON | Project Agreement End Date | 2029-04-29 |