This project will create an interconnected Traffic Signal System along the Skippack Pike Corridor. The project will include the installation of fiber optic cable on existing utility poles. The fiber optic interconnect is intended to be an extension of the existing fiber optic truck line installed along Route 202 and along Route 73 up to Wentz Road\Parkwood Road. The system will be connected with the PennDOT TMC and the Township will have viewing capabilities.
1. Skippack Pike and Wentz Road/Parkwood Road
2. Skippack Pike and Cathcart Road
3. Skippack Pike and Union Meeting Road
4. Skippack Pike and Pennlyn-Blue Bell Pike
5. Skippack Pike and Walton Road
6. Skippack Pike and Lewis Road
7. Skippack Pike and Nasrcissa Road
8. Skippack Pike and Butler Pike
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | CAQ | $145 | $0 | $0 | $0 | $0 |
Program Year Totals: | $145 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $145 | Total FY25-FY36 Cost: | $145 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Final Utility Clearance | |
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | 4232 Approved by FHWA | |
CON | Let | 2022-12-08 |
CON | Award Contract | 2023-01-07 |
CON | Notice to Proceed | 2023-01-23 |
CON | Start of Phase | 2023-02-06 |
CON | Completion of Phase | 2024-02-23 |
CON | Physical Work Complete | 2024-08-19 |
CON | Project Agreement End Date | 2025-06-24 |