114034 | US 322: Chelsea Parkway to Market St. Interchange (Section 103) (Delaware County)

This project involves widening and improving SR 322 to a four lane typical section with a median from Chelsea Parkway to the Market Street Interchange in Upper Chichester Township. The existing two lane section of SR 322 will be widened to four lanes with exclusive left turn lanes to accommodate left turns at the Cherry Tree Road / SR 3016 intersection. Auxiliary right turn lanes will be provided at multiple intersections. The Cherry Tree Road / SR 3016 intersection will be reconfigured and reconstructed including a new traffic signal, turn lanes, and realignment of Bethel Avenue. The existing four lane section from Cherry Tree Road to the Market Street interchange will be improved. The Market Street interchange will be reconstructed to a partial cloverleaf interchange including two new traffic signals and improvements made to Market Street.
•The total estimated cost for this project section is $80,000,000 in 2019 dollars).
•To make use of the available right of way, the Market Street interchange will be reconfigured as a partial cloverleaf configuration, including two new traffic signals.
•The anticipated let date is February 2023
•The anticipated completion date is October 31, 2026.

Limits: Chelsea Parkway to Market St. Interchange
Air Quality Code: 2035M

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
CONSTP*$579$0$0$0$0
CONNHPP*$0$19956$0$0$0
CONSTU*$2332$495$4087$3731$34430
Program Year Totals:$2,911$20,451$4,087$3,731 
Total FY25-FY28 Cost:$31,180Total FY25-FY36 Cost:$65,610 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONPhase on Approved STIP
CONLet2023-10-19
CONAward Contract2023-11-18
CONNotice to Proceed2023-12-18
CONStart of Phase2023-12-18
CONPhysical Work Complete2026-10-31
CONCompletion of Phase2026-12-30
CONProject Agreement End Date2028-04-30