113416 | Concrete Arch Bridges Rehabilitation (US 1)
SR 0001 (Township Line Road) over Cobbs Creek - The proposed scope of work includes removal of existing concrete bridge railing and replace with a new PA Type 10M bridge barrier (painted brown) attached to a moment slab; perform concrete repairs and crack repairs to the arch barrel; perform concrete repairs to the spandrel walls, wingwalls and abutments; improve off bridge drainage behind the wingwalls; install rock protection along the abutments and wingwalls; remove deposits and timber debris in the upstream and downstream channels; upgrade guide rail to current MASH standards; replace existing sidewalk; and repave the bituminous roadway and approach roadway. SR 0001 (City Avenue) over East Branch Indian Creek - The proposed scope of work includes replacement of cracked and settled sidewalk sections; removal of vegetation debris from the bridge; removal of vegetation growth from the bridge; remove tree at northwest quadrant of the bridge that is growing into the bridge railing; concrete repairs to the balustrade railing, matching color and texture to existing bridge; concrete repairs and crack repairs to the arch barrel, matching color and texture to existing bridge; concrete repairs to the spandrel walls, wingwalls and abutments, matching color and texture to existing bridge; repave bituminous roadway and approach roadway; and the installation of rock scour protection along abutments, using a dark colored stone that blends with the environment.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 185 | $500 | $0 | $0 | $0 | $0 |
ROW | TOLL | $0 | $0 | $0 | $0 | $0 |
ROW | STP | $100 | $0 | $0 | $0 | $0 |
UTL | STP | $100 | $0 | $0 | $0 | $0 |
UTL | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | STP | $0 | $0 | $1200 | $1200 | $0 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
Program Year Totals: | $700 | $0 | $1,200 | $1,200 | ||
Total FY25-FY28 Cost: | $3,100 | Total FY25-FY36 Cost: | $3,100 | |||
All costs in thousands. |