113312 | US 1 Expressway Reconstruction: PA 41 to Schoolhouse Road (East Marlborough Township, Kennett Township, London Grove Township & New Garden Township, Chester County)

The project consists of pavement rehabilitation and reconstruction; guiderail upgrades; vertical and lateral clearance compliance corrections of overhead structures; and interchange improvements such as length of acceleration and deceleration lanes and loop ramp radii. Interchanges included in the work are at Newark Road, PA 82, and Baltimore Pike. See also MPMS #14580, #14581, and #113307.

Limits: PA 41 to Schoolhouse Road
Air Quality Code: S10

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FD581$1853$3024$1755$0$0
ROW581$0$2289$1000$3485$0
UTL581$0$0$0$0$299
CONNHPP$0$0$0$2274$69918
CONBOF$0$0$0$0$3000
CONSTU$0$0$0$0$10274
CON581$0$0$0$2319$19801
Program Year Totals:$1,853$5,313$2,755$8,078 
Total FY25-FY28 Cost:$17,999Total FY25-FY36 Cost:$121,291 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
CONPhase Approved by PMC
UTLPhase Approved by PMC
ROWPhase Approved by PMC
FDPhase on Approved STIP
CONPhase on Approved STIP
FDStart of Phase2024-10-15
UTLPlan to Utility Unit2025-02-15
ROWPlan to ROW Unit2025-08-15
FDPS+E to District Contract Management2027-08-15
CONLet2027-11-04
CONAward Contract2027-12-04
CONStart of Phase2028-01-03
CONNotice to Proceed2028-01-03
FDCompletion of Phase2028-01-03
CONPhysical Work Complete2030-01-31
CONCompletion of Phase2030-04-01
CONProject Agreement End Date2031-08-01