113312 | US 1 Expressway Reconstruction: PA 41 to Schoolhouse Road (East Marlborough Township, Kennett Township, London Grove Township & New Garden Township, Chester County)
The project consists of pavement rehabilitation and reconstruction; guiderail upgrades; vertical and lateral clearance compliance corrections of overhead structures; and interchange improvements such as length of acceleration and deceleration lanes and loop ramp radii. Interchanges included in the work are at Newark Road, PA 82, and Baltimore Pike. See also MPMS #14580, #14581, and #113307.
Limits: PA 41 to Schoolhouse Road
Air Quality Code: S10
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 581 | $1853 | $3024 | $1755 | $0 | $0 |
ROW | 581 | $0 | $2289 | $1000 | $3485 | $0 |
UTL | 581 | $0 | $0 | $0 | $0 | $299 |
CON | NHPP | $0 | $0 | $0 | $2274 | $69918 |
CON | BOF | $0 | $0 | $0 | $0 | $3000 |
CON | STU | $0 | $0 | $0 | $0 | $10274 |
CON | 581 | $0 | $0 | $0 | $2319 | $19801 |
Program Year Totals: | $1,853 | $5,313 | $2,755 | $8,078 | ||
Total FY25-FY28 Cost: | $17,999 | Total FY25-FY36 Cost: | $121,291 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Start of Phase | 2024-10-15 |
UTL | Plan to Utility Unit | 2025-02-15 |
ROW | Plan to ROW Unit | 2025-08-15 |
FD | PS+E to District Contract Management | 2027-08-15 |
CON | Let | 2027-11-04 |
CON | Award Contract | 2027-12-04 |
CON | Start of Phase | 2028-01-03 |
CON | Notice to Proceed | 2028-01-03 |
FD | Completion of Phase | 2028-01-03 |
CON | Physical Work Complete | 2030-01-31 |
CON | Completion of Phase | 2030-04-01 |
CON | Project Agreement End Date | 2031-08-01 |