113307 | US 1 Expressway Reconstruction: PA/MD Line to PA 472 (West Nottingham Township, East Nottingham Township & Lower Oxford Township, Chester County)
The project consists of pavement rehabilitation and reconstruction; guiderail upgrades; vertical and lateral clearance compliance corrections of overhead structures; and interchange improvements such as length of acceleration and deceleration lanes and loop ramp radii. Interchanges included in the work are at Sylmar Road, Ridge Road, and PA 272. See also MPMS #14580, #14581, and #113312.
Limits: PA/MD Line to PA 472
Air Quality Code: S10
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | NHPP | $5304 | $0 | $0 | $0 | $0 |
ROW | 581 | $0 | $1311 | $0 | $0 | $0 |
UTL | STP | $0 | $0 | $0 | $0 | $261 |
UTL | 581 | $0 | $0 | $0 | $0 | $65 |
CON | STU | $0 | $0 | $0 | $2663 | $0 |
CON | 581 | $0 | $0 | $416 | $1353 | $14891 |
CON | STP | $0 | $0 | $1663 | $2748 | $59556 |
Program Year Totals: | $5,304 | $1,311 | $2,079 | $6,764 | ||
Total FY25-FY28 Cost: | $15,458 | Total FY25-FY36 Cost: | $90,231 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | Start of Phase | 2024-10-15 |
UTL | Plan to Utility Unit | 2025-02-15 |
ROW | Plan to ROW Unit | 2025-05-15 |
FD | PS+E to District Contract Management | 2027-05-15 |
CON | Let | 2027-08-15 |
CON | Award Contract | 2027-09-14 |
FD | Completion of Phase | 2027-10-14 |
CON | Start of Phase | 2027-10-14 |
CON | Notice to Proceed | 2027-10-14 |
CON | Physical Work Complete | 2030-06-30 |
CON | Completion of Phase | 2030-08-29 |
CON | Project Agreement End Date | 2031-12-29 |