112527 | Citywide ADA Ramps 3 (Philadelphia City)
This "Transition List" project will include the design and construction of ADA ramps that were originally included in the scope of other federal aid projects – primarily Center City Signals NE Quad (MPMS# 70014), completed in 2017, and the cancelled Citywide Bumpouts project (MPMS# 64805) – as well as various streetscape projects and ramps located on select Federal Aid routes that were repaved with local funding. These ramps typically would be included as design build items in the original project contracts, however, in some instances, the urban context of the ADA ramp locations warrants further coordination or study. To allow the original construction projects to proceed in a timely fashion, these ramps were pulled from the original construction contracts and will now be addressed as part of this transition list package. This will allow the City to design and construct the ramps to meet current ADA requirements while properly providing for stairs, cellar doors, unique paving materials, adjacent historic properties and other considerations as necessary.
Limits: City of Philadelphia
Air Quality Code: A2
FY2025 TIP for PA Program Years (in Thousands)
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|
FD | LOC | $347 | $0 | $0 | $0 | $0 |
FD | STP | $1384 | $0 | $0 | $0 | $0 |
CON | STU | $0 | $0 | $1880 | $0 | $0 |
CON | STP | $0 | $1880 | $0 | $880 | $4760 |
CON | LOC | $0 | $470 | $470 | $220 | $1190 |
Program Year Totals: | $1,731 | $2,350 | $2,350 | $1,100 | |
Total FY25-FY28 Cost: | $7,531 | Total FY25-FY36 Cost: | $13,481 | |
All costs in thousands. |
Milestones
Phase | Milestone | Estimated Date |
---|
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
PE | 4232 Approved by FHWA | |
PE | Start of Phase | 2020-04-15 |
PE | Completion of Phase | 2023-06-14 |
FD | Phase on Approved STIP | |
PE | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
PE | N. E. P. A. Approval | 2023-05-15 |
FD | Start of Phase | 2023-06-14 |
CON | Let | 2024-02-15 |
CON | Award Contract | 2024-03-16 |
CON | Start of Phase | 2024-04-15 |
FD | Completion of Phase | 2024-04-15 |
CON | Notice to Proceed | 2024-04-15 |
FD | PS+E to District Contract Management | 2024-08-14 |
CON | Physical Work Complete | 2026-08-15 |
CON | Project Agreement End Date | 2028-02-13 |
CON | Completion of Phase | 2028-07-23 |