111194 | Castor Avenue Corridor Safety Improvements (Philadelphia City)

This project will implement a road diet, upgrade signals, and add left turn lanes to the project area.

Limits: Castor Ave from Comly to Rhawn Ave
Air Quality Code: S6

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
CONTOLL$0$0$0$0$0
CONHSIP$6048$921$0$0$0
Program Year Totals:$6,048$921$0$0 
Total FY25-FY28 Cost:$6,969Total FY25-FY36 Cost:$6,969 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDStart of Phase2020-05-28
FDPhase Approved by PMC
CONPhase Approved by PMC
FD4232 Approved by FHWA
FDPhase on Approved STIP
CONPhase on Approved STIP
FDPS+E to District Contract Management2024-07-15
CONLet2024-10-10
CONAward Contract2024-11-09
CONStart of Phase2024-12-09
CONNotice to Proceed2024-12-09
FDCompletion of Phase2024-12-09
CONPhysical Work Complete2026-08-31
CONCompletion of Phase2026-10-30
CONProject Agreement End Date2028-02-29