111022 | Chichester Avenue Corridor Safety Improvements (Upper Chichester Township, Delaware County)
Chichester Avenue Corridor Safety Improvements include (1) the intersection of Bethel Road/Thornton Road – convert pedestal mounted signal to mast arm to improve visibility and (2) the intersections of Pleasant Ave./I-95 Ramp C and Johnson Ave./I-95 Ramp A/B – improve multimodal safety, using the Intersection Control Evaluation process, by converting the two-way stop controlled intersections to roundabouts pending the concurrence from the township.
This road segment is included in the Delaware County Bicycle Plan.
Limits: Laughead Ave. to Bethel/Thornton Rd.
Air Quality Code: 2030M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | sHSIP | $36 | $0 | $0 | $0 | $0 |
CON | sHSIP | $0 | $849 | $0 | $0 | $0 |
Program Year Totals: | $36 | $849 | $0 | $0 | ||
Total FY25-FY28 Cost: | $885 | Total FY25-FY36 Cost: | $885 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Start of Phase | 2024-06-26 |
FD | PS+E to District Contract Management | 2026-08-26 |
CON | Let | 2026-11-05 |
CON | Award Contract | 2026-12-05 |
FD | Completion of Phase | 2027-01-04 |
CON | Start of Phase | 2027-01-04 |
CON | Notice to Proceed | 2027-01-04 |
CON | Physical Work Complete | 2028-11-27 |
CON | Completion of Phase | 2029-01-26 |
CON | Project Agreement End Date | 2030-05-28 |