111022 | Chichester Avenue Corridor Safety Improvements (Upper Chichester Township, Delaware County)

Chichester Avenue Corridor Safety Improvements include (1) the intersection of Bethel Road/Thornton Road – convert pedestal mounted signal to mast arm to improve visibility and (2) the intersections of Pleasant Ave./I-95 Ramp C and Johnson Ave./I-95 Ramp A/B – improve multimodal safety, using the Intersection Control Evaluation process, by converting the two-way stop controlled intersections to roundabouts pending the concurrence from the township.
This road segment is included in the Delaware County Bicycle Plan.

Limits: Laughead Ave. to Bethel/Thornton Rd.
Air Quality Code: 2030M

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FDsHSIP$36$0$0$0$0
CONsHSIP$0$849$0$0$0
Program Year Totals:$36$849$0$0 
Total FY25-FY28 Cost:$885Total FY25-FY36 Cost:$885 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
FDPhase Approved by PMC
FDPhase on Approved STIP
CONPhase on Approved STIP
FDStart of Phase2024-06-26
FDPS+E to District Contract Management2026-08-26
CONLet2026-11-05
CONAward Contract2026-12-05
FDCompletion of Phase2027-01-04
CONStart of Phase2027-01-04
CONNotice to Proceed2027-01-04
CONPhysical Work Complete2028-11-27
CONCompletion of Phase2029-01-26
CONProject Agreement End Date2030-05-28