110971 | Main Street Safety Improvements (West Norriton Township, Montgomery County)
The project will implement a 4-lane partial “road diet” configuration along Main Street (SR 3009) between Egypt Road (SR 4002) and Forest Avenue/West Airy Street. The existing four-lane undivided roadway will maintain two (2) through lanes in the westbound direction, one (1) lane eastbound, and a shared left-turn lane throughout the project limits with dedicated turn lanes at the signalized intersections. In addition to the improvements along Main Street, the intersection of Main Street & Egypt Road/Jefferson Avenue/Orchard Lane will be reconstructed as a 5-leg “hybrid roundabout”. The “hybrid roundabout” will include a 2-lane exit for Main Street and a single lane exit for Egypt Road. Temporary and permanent right-of-way acquisitions will be required in the area of the “hybrid roundabout”. The existing traffic signals at Schuylkill Avenue, Whitehall Road, and Forrest Avenue/West Airy Street will be modified, as necessary. The ADA and pedestrian facilities along the corridor will be evaluated and updated, as necessary, to meet current ADA standards.
Limits: Main Street (SR 3009) corridor from Egypt Rd. to Airy St./Forrest Ave.
Air Quality Code: 2035M
FY2025 TIP for PA Program Years (in Thousands)
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|
ROW | sHSIP | $68 | $0 | $0 | $0 | $0 |
UTL | sHSIP | $0 | $34 | $0 | $0 | $0 |
CON | sHSIP | $0 | $4774 | $0 | $0 | $0 |
Program Year Totals: | $68 | $4,808 | $0 | $0 | |
Total FY25-FY28 Cost: | $4,876 | Total FY25-FY36 Cost: | $4,876 | |
All costs in thousands. |
Milestones
Phase | Milestone | Estimated Date |
---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2019-12-17 |
UTL | Start of Phase | 2019-12-17 |
UTL | Completion of Phase | 2020-03-17 |
ROW | Completion of Phase | 2020-05-17 |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2025-05-01 |
UTL | Plan to Utility Unit | 2025-05-15 |
CON | Let | 2026-04-23 |
CON | Award Contract | 2026-05-23 |
CON | Notice to Proceed | 2026-06-22 |
CON | Start of Phase | 2026-06-22 |
CON | Completion of Phase | 2026-11-14 |
CON | Physical Work Complete | 2027-06-03 |
CON | Project Agreement End Date | 2028-12-01 |