110958 | Castor Avenue Roundabout (Philadelphia City)
The project involves the reconstruction of the intersection of Castor Avenue (SR 1005) and Wyoming Avenue in the City of Philadelphia, PA from a rotary to a modern roundabout. This includes retrofitting the approach geometry and narrowing the circulatory roadway to slow the speeds of vehicles navigating the roundabout. Sidewalks and crossings will be upgraded for ADA compliance and bicycle ramps will also be installed to allow cyclists to navigate the roundabout as pedestrians. Trackless trolley poles will be relocated as needed and transit stops upgraded to accommodate transit users. Where possible the intersection will be milled/overlaid to avoid full depth reconstruction.
Limits: Castor Avneue (SR 1005) and Wyoming Avenue
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | sHSIP | $5072 | $0 | $0 | $0 | $0 |
Program Year Totals: | $5,072 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $5,072 | Total FY25-FY36 Cost: | $5,072 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final Utility Clearance | |
CON | Phase on Approved STIP | |
CON | Let | 2024-09-12 |
CON | Award Contract | 2024-10-12 |
CON | Start of Phase | 2024-11-11 |
CON | Notice to Proceed | 2024-11-11 |
CON | Physical Work Complete | 2025-12-15 |
CON | Completion of Phase | 2026-02-13 |
CON | Project Agreement End Date | 2027-06-15 |