110765 | Pickering Dam Road over Branch of Pickering Creek (Charlestown Township, Chester County)
This project involves rehabilitating or replacing the Bridge at Pickering Dam Road over Branch Pickering Creek in Charlestown Township.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: Charlestown Township
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | 185 | $82 | $0 | $0 | $0 | $0 |
UTL | 185 | $0 | $34 | $0 | $0 | $0 |
CON | 185 | $0 | $1107 | $1107 | $0 | $0 |
Program Year Totals: | $82 | $1,141 | $1,107 | $0 | ||
Total FY25-FY28 Cost: | $2,330 | Total FY25-FY36 Cost: | $2,330 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
PE | Phase on Approved STIP | |
PE | Start of Phase | 2022-10-01 |
FD | Start of Phase | 2024-04-10 |
PE | N. E. P. A. Approval | 2024-04-10 |
UTL | Plan to Utility Unit | 2024-04-10 |
ROW | Plan to ROW Unit | 2024-04-10 |
PE | Completion of Phase | 2024-10-01 |
UTL | Start of Phase | 2024-10-02 |
ROW | Start of Phase | 2024-10-02 |
FD | PS+E to District Contract Management | 2025-04-10 |
CON | Let | 2025-10-09 |
ROW | Completion of Phase | 2025-10-30 |
FD | Completion of Phase | 2025-10-30 |
UTL | Completion of Phase | 2025-10-30 |
CON | Award Contract | 2025-11-08 |
CON | Notice to Proceed | 2025-12-08 |
CON | Start of Phase | 2025-12-08 |
CON | Physical Work Complete | 2026-10-10 |
CON | Project Agreement End Date | 2027-04-10 |
CON | Completion of Phase | 2027-12-31 |