110763 | Cold Spring Creamery Road Bridge over Branch of Pine Run (Buckingham Township, Bucks County)
This project involves rehabilitating or replacing the Bridge atCold Spring Creamery Road over Branch Pine Run.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: Buckingham Township
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | 185 | $90 | $0 | $0 | $0 | $0 |
UTL | 185 | $0 | $31 | $0 | $0 | $0 |
CON | 185 | $0 | $867 | $978 | $0 | $0 |
Program Year Totals: | $90 | $898 | $978 | $0 | ||
Total FY25-FY28 Cost: | $1,966 | Total FY25-FY36 Cost: | $1,966 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Start of Phase | 2023-09-30 |
UTL | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
PE | Phase on Approved STIP | |
ROW | Phase Approved by PMC | |
ROW | Phase on Approved STIP | |
PE | Completion of Phase | 2025-09-30 |
UTL | Start of Phase | 2023-09-30 |
FD | Start of Phase | 2023-09-30 |
PE | N. E. P. A. Approval | 2023-09-30 |
UTL | Plan to Utility Unit | 2023-09-30 |
ROW | Plan to ROW Unit | 2024-09-30 |
ROW | Start of Phase | 2024-09-30 |
FD | PS+E to District Contract Management | 2025-03-30 |
CON | Let | 2025-09-25 |
CON | Award Contract | 2025-10-25 |
CON | Start of Phase | 2025-11-24 |
CON | Notice to Proceed | 2025-11-24 |
FD | Completion of Phase | 2025-11-24 |
CON | Physical Work Complete | 2026-09-25 |
CON | Completion of Phase | 2027-06-30 |
ROW | Completion of Phase | 2031-10-01 |
UTL | Completion of Phase | 2031-10-01 |