110762 | Perkiomenville Road over Sciota Creek Bridge Replacement (Upper Frederick Township, Montgomery County)
This project involves the replacement of the state-owned bridge located on Perkiomenville Road over Sciota Creek in Upper Frederick
Township, Montgomery County. The existing bridge, built in 1932, is a one-span concrete closed spandrel arch with a span length of 30
feet. The bridge is two lanes wide with no shoulders or sidewalk. The existing approach roadway is 21 feet wide with two lanes and no
shoulders or sidewalk. The bridge is currently posted at 36 tons/40 tons for combination.
Limits: Upper Frederick Township
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 185 | $179 | $0 | $0 | $0 | $0 |
ROW | 185 | $119 | $0 | $0 | $0 | $0 |
UTL | 185 | $0 | $25 | $0 | $0 | $0 |
CON | STU | $0 | $960 | $960 | $0 | $0 |
CON | 185 | $0 | $240 | $240 | $0 | $0 |
Program Year Totals: | $298 | $1,225 | $1,200 | $0 | ||
Total FY25-FY28 Cost: | $2,723 | Total FY25-FY36 Cost: | $2,723 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2019-10-01 |
UTL | Start of Phase | 2019-10-01 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
FD | Start of Phase | 2023-06-15 |
ROW | Plan to ROW Unit | 2023-06-15 |
UTL | Plan to Utility Unit | 2023-06-15 |
UTL | Completion of Phase | 2023-11-27 |
ROW | Completion of Phase | 2023-11-27 |
FD | PS+E to District Contract Management | 2024-06-15 |
CON | Let | 2024-09-26 |
CON | Award Contract | 2024-10-26 |
CON | Start of Phase | 2024-11-25 |
FD | Completion of Phase | 2024-11-25 |
CON | Notice to Proceed | 2024-11-25 |
CON | Physical Work Complete | 2025-11-28 |
CON | Completion of Phase | 2026-01-27 |
CON | Project Agreement End Date | 2027-05-29 |