110761 | Gilbertsvle Rd over Branch of Ministers Creek (Douglass Township, Montgomery County)
This project involves rehabilitating or replacing the Bridge at Gilbertsville Road over Ministers Creek.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: Douglass Township
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 185 | $137 | $0 | $0 | $0 | $0 |
ROW | 185 | $82 | $0 | $0 | $0 | $0 |
UTL | 185 | $55 | $0 | $0 | $0 | $0 |
CON | 185 | $0 | $146 | $0 | $0 | $0 |
CON | 581 | $0 | $585 | $0 | $0 | $0 |
Program Year Totals: | $274 | $731 | $0 | $0 | ||
Total FY25-FY28 Cost: | $1,005 | Total FY25-FY36 Cost: | $1,005 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Start of Phase | 2022-10-01 |
FD | Start of Phase | 2023-07-10 |
UTL | Start of Phase | 2023-07-10 |
PE | N. E. P. A. Approval | 2023-07-10 |
ROW | Plan to ROW Unit | 2023-07-10 |
PE | Completion of Phase | 2023-08-09 |
ROW | Start of Phase | 2023-10-02 |
FD | PS+E to District Contract Management | 2024-07-10 |
UTL | Plan to Utility Unit | 2024-07-10 |
UTL | Completion of Phase | 2024-10-02 |
ROW | Completion of Phase | 2024-10-02 |
CON | Let | 2024-10-10 |
CON | Award Contract | 2024-11-09 |
FD | Completion of Phase | 2024-12-09 |
CON | Notice to Proceed | 2024-12-09 |
CON | Start of Phase | 2024-12-15 |
CON | Physical Work Complete | 2025-10-10 |
CON | Completion of Phase | 2026-06-30 |
CON | Project Agreement End Date | 2027-04-10 |